Project detail:
Purpose/Need: To undertake mining of Soft Murram, Hard Murram and Black Trap to meet the increasing demand from the construction and infrastructure sectors in the region. Project Activity/Process: Mechanized opencast mining of Soft Murram, Hard Murram and Black Trap. The mining operations include excavation, sorting and transportation of minerals by trucks. Capacity: Soft Murram – 27,893 MTPA; Hard Murram – 36,803 MTPA; Black Trap – 2,00,000 MTPA (Total: 2,64,696 MTPA) over a lease area of 1.61.88 hectares. Employment/Infrastructure/Economic Importance: The project will generate employment for approximately 11 direct workers (with around 15 direct and indirect employment opportunities mentioned in the executive summary), contribute royalty revenue to the State, support local infrastructure such as schools and water facilities, and promote regional socio-economic development.
Project Cost: ?6,83,24,040/-
Note: please download project document attached to this project for more information.
|