Project Detail:
Type of Project Including Interlinked and Interdependent Projects, If Any. The mine is over an area of 22.056 Hect. The proposed production is 1,15,796.25 MTPA This is an independent mining project and there are no interlinked projects involved.
Details of Alternate Sites, Mining is site specific so no alternative site is proposed.
Size or magnitude of operation, The mining lease has been granted over an area of 22.056 Hect. During Five-year total production of Limestone shall be approximately 1,15,796.25 MTPA. The average number of working days in the year would be 300.
Total Project Cost: Cr. 10.8070176
Note: Please Download Project Document attached to this Project for more information.
|