Project Detail:
The details of the project, as per the documents submitted by the project proponent, and also as informed during the above said EAC meeting, are reported to be as under M/s Cochin Shipyard Ltd has proposed for augmentation of existing ship repair facility at Cochin Port of District Ernakulam, Kerala. Existing Cochin Ship Repair Facility was established in 1938 at Wellingdon Island with a dry dock and one afloat berth having the following features: i) Dry Dock — 66m length, 12.5m width and 4m depth ii) Two Cranes iii) Afloat repair berth of 90m length without any crane capacity Existing facility is capable of only accommodating maximum size of ships length 64m, breadth 5 12.5 and draught of 4m. Total area required for the proposed project is 17 ha (Land) + 15 ha (water front) area.
The total cost of the project is Rs. 970.00 crores.
Note: Please Download Project Document attached to this Project for more information.
|