Subscription

Central Government/Public SectorProject Information Greenfield Project with Installation of 2 x 9 MVA Submerged Arc Furnace (SAF) to make 35,176 TPA Ferro Manganese / Silico Manganese / Ferro Chrome / Silico Chrome/ Ferro Silicon) and 2 x 4.5 MVA Electric Arc Furnace (EAF) to make 29,700 TPA Low Carbon Ferro Chrome at Mouza: Chausal, PS: Gangajalghati, District- Bankura, West Bengal by M/s Hariaksh Industries private Limited. INR 92.56 Cr INR 925.60 Mn
08-Jun-2023
PID : 61378 West Bengal-India

Project Detail:

The instant proposal is for installation 2 x 9 MVA Submerged Arc Furnace (SAF) to make 35,176 TPA Ferro Manganese / Silico Manganese / Ferro Chrome / Silico Chrome/ Ferro Silicon) and 2 x 4.5 MVA Electric Arc Furnace (EAF) to make 29,700 TPA Low Carbon Ferro Chrome’ for production of Ferro Manganese / Silico Manganese / Ferro Chrome / Silico Chrome/ Ferro Silicon 35,176 tonnes per annum(TPA) & Low Carbon Ferro Chrome 29,700 tonne per annum (TPA).

The EAC, constituted under the provision of the EIA Notification, 2006 comprising Expert Members/domain experts in various fields, examined the proposal submitted by the Project Proponent in desired format along with EIA/EMP reports prepared and submitted by the Consultant accredited by the QCI/ NABET on behalf of the Project Proponent.

The EAC noted that the Project Proponent has given an undertaking that the data and information given in the application and enclosures are true to the best of his knowledge and belief and no information has been suppressed in the EIA/EMP reports. If any part of data/information  submitted is found to be false/ misleading at any stage, the project will be rejected and Environmental Clearance given, if any, will be revoked at the risk and cost of the project proponent.

The Committee noted that the EIA reports are in compliance of the ToR issued for the project, reflecting the present environmental status and the projected scenario for all the environmental components. The Committee deliberated on the proposed mitigation measure towards Air, Water, Noise and Soil pollutions. The Committee suggested that the storage of toxic/explosive raw materials/products shall be undertaken with utmost precautions and following the safety norms and best practices.

The total project area is 4.20 ha which is under the possession of M/s Hariaksh Industries Private Limited. The same is Converted to Industrial, as per Letter from District Planning Cell, Bankura, West Bengal, vide letter no. memo no. 943/DPC/BGPA on dated 10/01/2018.

The water requirement for the project is estimated as 350 m3/day, including 5 m3/day of freshwater requirement for domestic use will be sourced from the Surface water.

Damodar River is at a distance of 7.2 km from the project site in the NE direction. The EAC is of the opinion that water body shall not be disturbed. Mitigation measures w.r.t. safeguarding the water body shall be implemented.

The capital cost of the project is Rs 92.56 Cr

Note: Please Download Project Document attached to this Project for more information.

Subscribe our annual Project Alert Service and get access to all similar Projects.If you are registered member, please fill in the subscription form below . If not, please Register first.

(*) Mandatory fields
Select Plan Unit Rate Subscription Validity
Rs. 25000 /- 1 Year
Rs. 40000 /- 1 Year
Rs. 60000 /- 1 Year
Rs. 50000 /- 1 Year
Rs. 75000 /- 1 Year
Rs. 125000 /- 1 Year
* Service Tax As Applicable

Note : As Goods and Services Tax is set to be implemented from 1st July 2017. The transition provisions under GST law applies to all services provided by e-Procurement Technologies Ltd. to its clients on or after 1st July 2017 and GST tax rate and other taxes are applicable as extra for all services provided.

Top