Project Detail:
Standard ToR and Public Hearing is not applicable as the project falls under category B2 as per OM dated 16th June, 2021. It was informed that there is no litigation is pending against the project.
Total land area required is 7.59 hectares. Greenbelt will be developed in 2.5 hectares land i.e., 33% of total project area. The estimated project cost is INR Rs. 190.15. Crores. Capital cost of EMP would be INR Rs. 28.5 Crores and recurring cost for EMP would be INR Rs. 7.15 Crores per annum. Industry proposes to allocate Rs. 3.0 Crores towards Extended EMP (Corporate Environment Responsibility). Total Employment will be 145 persons as direct & indirect.
There are no national parks, wildlife sanctuaries, wildlife corridors etc. within 10 km distance. Conservation plan for schedule I species has been submitted to PCCF, Lucknow and a budget of 0.05 Crores has been earmarked for the same Reserve Forest is at 4.1 km towards NE; Pond is at 0.2 km towards WSW; Aril Nadi is at 1.5 km towards E; Bahata Nala is at 3 km towards SW; Purnihai Talab is at 3.3 km towards E; Sot Nadi is at 4.5 km towards SW. Flood NOC for pond has been obtained from office executive engineer, Sharda Canal Section, Shahjahanpur dated 21.03.2023.
AAQ modelling study for point source emissions indicates that the maximum incremental GLCs after the proposed project would be 0.24 μg/m3, 0.1 μg/m3, 0.41 μg/m3, 1.21μg/m3 and 1.06 μg/m3 with respect to PM10, PM2.5, SO2, NO2 and CO. The resultant concentrations are within the National Ambient Air Quality Standards (NAAQS).
The estimated project cost is INR Rs. 190.15. Crores.