Project detail:
The Ministry of Environment, Forest and Climate Change has examined the proposal seeking environmental clearance for establishment of 150 KLD Grain Based Ethanol Plant along with 4.5 MW Cogeneration Power Plant located at Khasra no. 239/1, 239/2 KHA, Village-Natwarpur, Tehsil & District-Raigarh, Chhattisgarh by M/s. B R Refinery LLP.
Total land area required is 5.52 hectares. Greenbelt will be developed in total area of 1.82 hectares i.e., 33% of total project area. The estimated project cost is INR Rs. 198 Crores. Capital cost of EMP would be INR Rs. 29.2 Crores and recurring cost for EMP would be INR Rs. 3.15 Crores per annum. Industry proposes to allocate Rs. 3.00 Crores towards Extended EMP (Corporate Environment Responsibility). Total Employment will be 70 persons as direct & indirect.
Note: please download project document attached to this project for more information.
|