I am directed to convey the grant of Administrative Approval and Expenditure Sanction (AA&ES) for the project “Interception & Diversion and STP scheme for Lakhisarai town, Bihar” under National Ganga Plan (NGP) — Non EAP budget head of Namami Gange Mission — II, with 100% central sector support at an estimated cost of Rs 94.12 Crore (Rupees Ninety Four Crore and Twelve Lakh only).
Development of 2 STPs (STP-1: 11 MLD; and STP-2: 11 MLD) including necessary ancillary infrastructures, UV disinfection, SCADA and online monitoring system.
The period of completion of the project is 24 (Twenty Four) months which includes, 3 months for bidding and 3 months of trial run. The procurement of goods and services shall be made strictly as per the ‘NGRBA programme framework’ and various other guidelines of NMCG. The detailed schedule of the project implementation.