Project detail:
I am directed to convey the grant of Administrative Approval and Expenditure Sanction for the project on “Interception & Diversion and STP works in Dhanbad town, Jharkhand” under National Ganga Plan (NGP) — Non-EAP budget head of Namami Gange Mission — II, with 100% central sector support at an estimated cost of Rs. 808.33 Crore (Rupees Eight Hundred Eight Crore and Thirty Three Lakh only).
The period of completion of the project is 36 (Thirty Six) months from the date of issue of AA&ES (excluding the period of trial run) which includes, 3 months for bidding and 33 months for construction. The procurement of goods and services shall be made strictly as per the ‘NGRBA programme framework’ and various other guidelines of NMCG.