Project detail:
I am directed to convey the grant of Administrative Approval and Expenditure Sanction for the project on “Interception & Diversion and STP scheme for Motihari town, Bihar” under National Ganga Plan (NGP) — Non EAP budget head of Namami Gange Mission — II, with 100% central sector support at an estimated cost of Rs 149.15 Crore (Rupees One Hundred Forty Nine Crore and Fifteen Lakh only)
The period of completion of the project is 33 (Thirty-three) months which includes, 3 months for bidding and 30 months for construction from the date of issue of AA&ES (excluding the period of trial run). The procurement of goods and services shall be made strictly as per the ‘'NGRBA programme framework’ and various other guidelines of NMCG.