Project detail:
1) Civil engineering and architectural work: Structure construction works including roadbed, bridges, freight stations, and junction stations
2) Truck laying work: Rail laying, etc.
3) Electric and mechanical work: Development of overhead lines, substations, etc.
4) Signal and communication work: Development of a signal and communication system
5) Railroad vehicle procurement: Electric locomotives (50 units of 6,000-horsepower and 150 units of 9,000-horsepower locomotives)
6) Consulting service: Construction supervision, quality and safety control, assistance in commissioning, review of operation and maintenance manuals, establishment of operation and maintenance plans, assistance in project implementation (including the implementation of training programs), implementation of environmental control and resident relocation monitoring plans, social development (publication, resident enlightenment activity, HIV/AIDS prevention activity), etc.
Estimated Project Cost: 403,258 million Yen (Japanese ODA loan (for the tranche III): 116,520 million Yen)
Schedule: July 2010 to May 2027 (203 months in total) Project Completion is defined as that all facilities are put in service (in May 2025).
Note: Please download project documents attached to this project for more information.
|