Project Detail:
Jilling Langalotta Iron Ore Block over an area of 456.037 ha (as per DGPS)/465.100 ha ha (as per RoR) in village Jalahari, Jurudi, Banspani, Khuntapani, Bholebeda, Jajang, Baitarani Reserve Forest. etc. under Barbil Tahasil of Keonjhar district for a period of 10 (ten) years.
This is the iron ore production over 10 MTPA (ROM) with screening and crushing facility within the existing ML area. Method of mining will be mechanized open cast. The ore produced from this mine will meet the ore requirement of the steel plant/ pellet plant/ sponge plant in the immediate vicinity and also for the nation.
The proposed project cost is 431 Crore