Project Detail:
Expansion of Kachche Aridongri Iron Ore Mine for enhancement of production from 1.405 MTPA to 2.35 MTPA (Incl. 0.55 MTPA BMQ), Installation of BMQ Beneficiation Plant of 0.6 MTPA Capacity, 250 TPH Iron Ore Screening Plant with Magnetic Separators for Processing of Low-Grade Ore and Dolerite Crushing & Screening Plant of 2 MTPA, within the Existing mining lease area of 138.96 Ha
The cost of the Project (capital cost and recur ring cost) as well as the cost towards implementation of EMP should be clearly spelt out.
The project is Rs. 6,145 Lakhs.
The environment management cost is Rs. 269.253 lakhs as a capital cost
and Rs. 28.71 for recurring expenditure
Note: Please Download Project Document attached to this Project for more information.
|