Nauru is a Pacific island country with a total population of 10,000 people. Access to grid electricity is universal, but unreliable, due to underinvestment and poor maintenance history of its generation and distribution assets. Installed generation currently comprises eight units with a total nameplate capacity of 12.9 megawatts (MW). However, Nauru's available capacity is only 3.7 MW due to inoperability (two units) and de-rating of installed units. Current peak load is 3.75 MW. Scheduled curtailments are a constant feature of electricity service in Nauru and unscheduled outages due to faults are frequent. The physical structure of the power house at Nauru Utility Corporation (NUC) is likewise in poor condition and is vulnerable to Nauru's electricity supply security. Addressing reliability and efficiency shortcomings in Nauru's current diesel generation fleet is of the first-order priority to mitigate the risk of catastrophic failure of Nauru's power generation.
The ongoing Nauru Electricity Supply Security and Sustainability Project (the project) has three out puts: (i) New diesel-fired generation put into service: a new, medium-speed, 2.6-3.0MW diesel generator will be installed, together with related auxiliary equipment and NUC personnel will be trained on its operation and maintenance; (ii) Repair and/or replacement of existing roof and structural reinforcements of NUC's powerhouse: the NUC powerhouse roof will be rehabilitated and all asbestos will be removed and safely disposed; (iii) Efficient project implementation: NUC will be assisted by a project management unit (PMU) with services of international consultants during project implementation .
The project was approved by the Asian Development Bank (ADB) on 7 November 2014. The project is financed by a grant 0414-NAU of $2.00 million from ADB's Special Funds resources (Asian Development Fund [ADF]), and a cofinancing grant 0424-NAU of 2.00 million ($2.70 million equivalent), provided by the EU, and fully administered by ADB. ADB and the EU concluded a contribution agreement and will finance project costs in three installments. Both grants became effective as of 16 April 2015. The government will provide contributions in-kind equivalent to $0.57 million, and in taxes and duties exemptions of $0.27 million. The government will make the proceeds of the grants available to the NUC under the subsidiary grant agreement signed between the government and NUC. The total project cost was estimated at $5.54 million.
The project's impact will be increased economic activity; all NUC customers will enjoy more dependable supply with fewer outages, and the NUC will resume supply to commercial and industrial customers. The project's outcome will be increased reliability, lower cost, and greater sustainability of power generation in Nauru. The incidence of power outages is expected to decrease by 50% by March 2017, and generation efficiency is expected to increase from 3.4 kWh per liter of fuel consumed to 4.1 kWh. The peak load is expected to increase by 20%.
The selection of design and supervision consultant (DSC) for PMU under the project was completed in 29 April 2015 and the consultants are currently engaged on preliminary investigations, consultations with NUC staff and preparing project implementation plan for the delivery of project outputs. The project Inception Mission by ADB was completed from 7-10 June 2015 in Nauru and a Memorandum of Understanding was signed between NUC and ADB on the agreements reached during the Mission. In accordance with the latest revised project schedule, the award of roof and generator contacts will be in February 2016. The expected date of completion of roof contract will be in August 2016 and generator contract will be in March 2017.
|