Project Detail:
The Project 20r to Chortennyima La Road starts from 20r & terminates at Chortennyima La in the state of Sikkim. The actual design length of the proposed alignment is 26.94 km.
The road proposed along the approved alignment is required by ITBP in order to establish connectivity between its Border Outposts at 20r ZANAK CHORTENNIMA. The military preparedness and security benefits are particularly critical in this region given the long – standing border and territorial issues with India’s Eastern neighbor, China which makes road connectivity of paramount importance so as to ensure easy mobilization of troops, artillery etc. as and when required.
Lenght: 26.94 Km
Width: Right of Way of 18 m and Carriageway of 3.75 m
No. of Bridges: 00 Nos. of 40 m Span Bailey Bridges
No. of Cross Drainage Works: 14
Period of Construction: 7 Years
Cost: 174.17 Crores