Project Title :NHPC completes trial run of Unit 2 at Parbati-II Hydroelectric Project
Company Name : National Hydroelectric Power Corporation Limited
Project Detail :NHPC has successfully completed the trial run for Unit 2 (200 MW) of the Parbati-II Hydroelectric Project in Himachal Pradesh on 24 March, 2025.

The project, with a total capacity of 800 MW (four units of 200 MW each), has faced significant delays since its inception in 2003 due to tunneling issues, water and silt seepage, flash floods, and adverse geological conditions. Originally set for commissioning in 2010, NHPC now aims to complete trial runs for the remaining units by 31 March, 2025. The completion of Unit 2's trial run is a crucial milestone in achieving full operational capacity.

Once fully commissioned, the Parbati-II project is expected to generate approx. 3,074 million units (MU) of electricity annually, strengthening India's renewable energy infrastructure. Additionally, its operation is expected to mitigate flood risks along the Parbati River, benefiting areas from Barshaini in the Manikaran Valley to Bhuntar.
Project Location : Not Classified - Himachal Pradesh - India
Project Industry :Power Plant
Project Estimation :Refer Document
Status :Announced