Project Title :Setting Up Integrated Steel Plant In Chhattisgarh.
Company Name : Godawari Power And Ispat Limited
Project Detail :The Board of Directors of Godawari Power and Ispat (GPIL) has in principle approved the proposal for setting up integrated steel plant with a capacity of 1.5 to two million tonne of flat products in the state of Chhattisgarh under Production Linked Incentive (PLI) Scheme

The estimated capital outlay would be around Rs 3,000 to Rs 4,000 crore

The company has initiated the process for land acquisition, obtaining environmental clearances, etc for setting up the said project.The final cost of the project will be finalised in due course

The Board also approved investment up to Rs 70.20 crore for acquisition of additional equity shares proposed to be offered by Hira Ferro Alloys (HFAL) on preferential basis to GPIL, subject to approval of shareholders of HFAL

HFAL is an associate company of GPIL, in which GPIL is already holding 48.45 percent of the equity share

Consequent upon aforesaid further investment, HFAL will become subsidiary of the company with 56.45 percent of enhanced share capital of HFAL

HFAL, engaged in the business of manufacturing ferro alloys is setting up 70 MW solar power plant in Rajnandgaon, Chhattisgarh, for its captive use with a project cost envisaged at Rs 230 crore

The project will be financed partially through equity and partially through bank finance

Project Location : Not Classified - Chhattisgarh - India
Project Industry :Stainless Steel
Project Estimation :Refer Document
Status :Announced