Project Title :Power Units Project Expansion In Chhattisgarh
Company Name : Ministry Of Environment, Forestry & Water Administration (Albania.)
Project Detail :The Ministry of Environment, Forest and Climate Change (MoEF&CC) has accorded terms of reference (ToR) to Godawari Power and Ispat for expansion and modernisation of existing facilities

The project will be located at 428/2, Phase-I, Industrial Area, Siltara, Raipur, in the state of Chhattisgarh

The expansion and modernisation of the existing manufacturing units and setting up of new units include -- sponge iron plant to 6,50,000 tpa, capacity enhancement of steel melting shop from 4,00,000 tpa to 7,00,000 tpa; power generation 73 MW; ferro alloys 16,500 tpa; pig iron 33,000 tpa; HB wire 1,00,000 tpa; iron ore beneficiation plant 10,00,000 tpa; rolling mill 4,00,000 tpa

The project also involves induction furnace for casting in place of arc furnace 5,000 tpa; iron ore pellet plant from 21,00,000 tpa to 24,00,000 tpa; slag crushing plant 1,75,000 tpa and mineral grinding unit 2,00,000 tpa

The land area in possession for the existing plant is 86.464 ha which is industrial land. Additionally, acquired land is 7.361 ha for the proposed expansion. The existing and proposed projects will be located in the total area of 93.825 ha

The cost of the project is approximately Rs 2,040 crore. The total electricity load will be 138.5 MW post-expansion

The ore for the proposed expansion will be procured from captive iron ore mines at Ari Dongri, Kanker, Chhattisgarh & Boria Tibbu district, Rajnandgaon district, Chhattisgarh via iron ore crushing unit at Gidhali, Balod district, Chhattisgarh and local market/ Odisha mines

Project Location : Raipur - Chhattisgarh - India
Project Industry :Non Conventional Energy
Project Estimation :INR 2040 Cr / INR 20.4 Bn
Status :Announced