Project Detail:
The proposed ropeway system will aid as a better transportation alternative in the area that will eventually accentuate tourism & socio-economic status in the area. The ropeway will cover a total land area of 84128 m?2 (8.4128 ha.). Out of which, 11450 m?2 will be forest land. The total inclined length will be 3675 m. There will be a continuous ropeway line from LTP to UTP along with ITP for balancing of haul rope tension between LTP & UTP.
The estimated project cost will be Rs 36 Crores.
The scheduled completion date will occur after 32-36 months from the grant of Environmental Clearance. On or before the scheduled completion date, the concessionaire will have completed the construction of the entire project.
Note: Please Download Project Document attached to this Project for more information.
|