Details of alternate sites considered and the basis of selecting the proposed site, particularly the environmental considerations gone into should be highlighted:
Mining is site specific project. The lease has been granted by the district authority for mining of Dolomite Stone , hence alternative site is not applicable.
Size or Magnitude of Operation:
The total lease area is 1.927 hectare and total proposed maximum production capacity will be 114160 TPA through Open Cast Mechanized method of mining with low level intensity scientific controlled blasting. Proposed production details during lease period are shown in below.
Total Project Cost: 27.74 Lakh