Project Detail:
Now it is proposed for expansion of existing Tube Mill from 29,000 TPA to 2,11,000 TPA, and establishment of new DRI Kilns to produce Sponge Iron of 4,26,000 TPA, Induction Furnaces along with CCM & LRF to produce Hot Billets /Billets/Ingots of 4,00,000 TPA, Rolling Mill along with Reheating Furnace to produce TMT/Strip/Structure of 3,60,000 TPA (through 85% Hot Charging with Hot Billets & 15% through RHF), Wire Mill to 6,000 TPA, Galvanization Plant of capacity of 72,000 TPA, Power generation through WHRB of 32 MW, through FBC of 14 MW & Fly Ash Brick making unit to produce 32,200 bricks/day.
Estimated Capital Investment for the proposed expansion project is Rs. 495.86 Crores.
Note: Please Download Project Document attached to this Project for more information.
|