Project Detail:
It is proposed to setup a Steel Plant with the following facilities:
Establishment of 2 x 350 TPD DRI Kilns to manufacture 2,31,000 TPA of Sponge Iron.
Establishment of 4 x 20 T of Induction Furnaces to manufacture 2,64,000 TPA of Hot Billets / MS Billets / Ingots.
Establishment of Rolling Mill to manufacture 2,64,000 TPA of TMT bars / Structural Steel (85 % Hot charging with Hot Billets and remaining 15% through RHF with LDO as fuel).
Estblishment of 2 x 32 TPH Waste Heat Recovery Boiler (WHRB) to produce 16.0 MW Electricity.
Establishment of 1 x 36 TPH Circulating Fluidized Bed Combustion (CFBC) Boiler to produce 9.0 MW Electricity.
Establishment of Brick manufacturing unit 32,000 Brick / day.
Estimated Project Cost for the proposed project is Rs. 350 Crores.