State GovernmentProject Information Implementing the Metro Project between Central Silk Board to K R Puram on Outer Ring Road. INR 4202 Cr INR 42.02 Bn
14-Oct-2021
PID : 50168 Karnataka-India

Project Detail:

Approval of Government of Karnataka (GoK) for implementing the Metro Project between Central Silk Board to K R Puram on Outer Ring Road for a length of 19.45 Km by BMRCL at a cost of Rs. 4202 Cr based on July 2016 prices was communicated
vide G.O UDD 78 PRJ 2016 dated 15.03.2017. Following the approval, part funding from Government of India (GoI) was requested. The GoI sought several clarifications in respect of the proposal for meeting the norms and requirements set out on subsequent introduction of Metro Rail Policy in August 2017.
The project is proposed to be implemented as Phase-2A for Bengaluru Metro in a period of 45 months from financial closure i.e. between April 2020 and December 2023. A suggested project implementation schedule is given in table below. Activity 6 i.e., commencement of piling in April 2020 will be the effective physical start of works and the Activities 1 to 5 will be the time required for approvals and preparatory works.

Note: Please Download Project Document attached to this Project for more information.

Subscribe our annual Project Alert Service and get access to all similar Projects.If you are registered member, please fill in the subscription form below . If not, please Register first.

(*) Mandatory fields
Select Plan Unit Rate Subscription Validity
Rs. 25000 /- 1 Year
Rs. 40000 /- 1 Year
Rs. 60000 /- 1 Year
Rs. 50000 /- 1 Year
Rs. 75000 /- 1 Year
Rs. 125000 /- 1 Year
* Service Tax As Applicable

Note : As Goods and Services Tax is set to be implemented from 1st July 2017. The transition provisions under GST law applies to all services provided by e-Procurement Technologies Ltd. to its clients on or after 1st July 2017 and GST tax rate and other taxes are applicable as extra for all services provided.

Top